Repository source: docs/plans/effort_ledger/push_subscribe.md
Cycle v3/push_subscribe
| Stable cycle ID | Status | Scope / reference / protocol | Projected total | Canonical checkpoints | Parent / acceptance |
|---|---|---|---|---|---|
v3/push_subscribe | Step 4 complete; merge, deploy and iPhone replay pending | v1 / R1 / P2 | 0.75; retrospective 0.80 | Step 1, Step 2, Step 3, Step 4 | Notifications checklist cycle 2; follows v3/owa_start_url |
2026-11-23 UTC — Standing P2 enrollment. Inherited checklist estimate 0.70. Intake after reading the reuse points and a crypto probe (no pristine intake), single exposed Claude rater. Step 1 alternatives A 0.70, B 0.70, C 0.90 (not summed); recommended A 0.70. Baseline 9f73088e.
2026-11-23 UTC — Step 1 approved (Option A, assumptions accepted). Step 2 handoff 0.75 (new understanding: sign-out hook tied to the session, device cap, PHP 8.1 key import check). Same rater and baseline.
2026-11-24 UTC — Step 2 approved. Step 3 handoff 0.75, unchanged; five stages (stage work 0.15, 0.10, 0.20, 0.20, 0.10, not summed). Same rater and baseline.
2026-11-24 UTC — Step 3 approved. Step 4 entry: 0.75 reaffirmed. Planning commit 80cadf01.
2026-11-24 UTC — Step 4 closeout: five stages committed (stage retrospectives 0.10, 0.10, 0.25, 0.20, 0.10, not summed). Cycle retrospective 0.80 (projected 0.75): a fourth route and a pre-existing test fix. Maintainer judgment and the iPhone replay pending.